The contract for the road in Arzamas for 2.6 billion rubles was not extended after the deadlines were missed.
11:59 July 14 Vasilyeva Anna
photo by "Pro Gorod"
The Arbitration Court of the Nizhny Novgorod Region did not satisfy the claim of the St. Petersburg company LLC SK "Orion Plus", which requested an extension of the contract for the construction of a road from Vyyezdnoye to the Arzamas-1 station. The deadline for completion was set for March 2026. This was reported by "Kommersant".
The contractor referred to delays in obtaining construction permits, project adjustments, and the discovery of unaccounted engineering networks. However, the court denied the request, stating that the deadlines had already been extended previously and that it was not possible to force the customer to change the terms of the contract through the court. The contract worth 2.6 billion rubles was signed in October 2022 with the regional GUAD. Initially, the completion of the 5.2 km road as part of the "Arzamas - Diveyevo - Sarov" project was planned for January 2025, but in December 2023, the deadline was shifted to March 2026. The work was delayed due to the discovery of intersections of gas, water, and railway communications in the area, as well as the need to rearrange the networks of "Gazprom Gas Distribution Nizhny Novgorod" and "Rosseti". Additional difficulties arose due to unaccounted volumes of work on strengthening the embankment over a length of 1.7 km and the requirements of RZD for the installation of a monitoring system during the construction of the overpass. In addition, the contractor pointed to delays in the issuance of a construction permit by the Arzamas administration.
Since 2023, the company has notified the customer of problems and suspended work. By the time the claim was filed in May 2025, the unworked advance amounted to 526.9 million rubles with a total amount of received funds exceeding 2 billion rubles. According to the contract, work worth 1.6 billion rubles has been completed to date, with actual payments of about 2 billion rubles. The contractor stated that it could not return the advance and complete the work without undergoing an examination of the updated project, which currently does not account for additional work. The court acknowledged that the delays were not the fault of the contractor, but deemed the arguments insufficient to change the terms of the contract. The decision stated that the legislation does not allow for the protection of the contractor's interests by forcing the customer to adjust the contract.
The construction of the road continues outside the framework of the existing contract. The head of Arzamas, Alexander Shchelokov, reported that the project is expected to be completed in winter, aiming for December. According to him, after the proceedings, penalties may be imposed on the contractor for failing to meet deadlines. Previously, the company was fined 4.9 million rubles in December 2025, and no new claims from GUAD have been announced yet.
More news about the event:
The contract for the road in Arzamas for 2.6 billion rubles was not extended after the deadlines were missed
11:59 July 14
Vasilyeva Anna
photo by "Pro Gorod"
The Arbitration Court of the Nizhny Novgorod Region did not satisfy the claim of the St. Petersburg company LLC SK "Orion Plus",14:18 14.07.2026 ProGorodNN.Ru - Nizhny Novgorod
The court denied the contractor an extension of the road construction deadlines in Arzamas
The contract for the new road will not be changed, despite delays and additional work. The court denied the contractor an extension of the road construction deadlines in Arzamas.13:22 14.07.2026 Komsomolskaya Pravda - Nizhny Novgorod
"Orion Plus" was fined for the delay in road construction in Arzamas
The Arbitration Court of the Nizhny Novgorod Region denied the construction company LLC SK "Orion Plus" an extension of the contract for the construction of a new road from the working village of Vyyezdnoye to the Arzamas-1 railway station.12:15 14.07.2026 Otkryty Nizhny - Nizhny Novgorod
The court denied the contractor an extension of the contract for the construction of the road in Arzamas
Photo: Kira Mishina
The Arbitration Court of the Nizhny Novgorod Region denied LLC SK "Orion Plus" in its claim against the Main Department of Automobile Roads of the region for an extension of the state contract for the construction of the road from 11:58 14.07.2026 NIA Nizhny Novgorod - Nizhny Novgorod
News from neighboring regions on the topic:
In Angarsk, the construction of the Marriage Palace has been suspended
This was reported by the Ministry of Construction of the Irkutsk Region. The contract with the contractor was signed on September 26, 2025, but work was halted due to a delay in the advance payment.11:38 16.07.2026 Aktis TV Company - Angarsk
St. Petersburg will allocate over 70 billion rubles for tram and trolleybus transportation
SPb GKU "Transport Organizer" is looking for contractors to carry out tram and trolleybus transportation in the Northern capital.12:20 15.07.2026 St. Petersburg TV - St. Petersburg
We report on the collection of taxes and fees administered by the Federal Tax Service of Russia for January - June 2026
In the first half of 2026, the consolidated budget of the Saratov Region received 72.9 billion rubles in taxes and fees administered by the Federal Tax Service of Russia, which is 6.7 billion rubles or 10.1% higher than the level of January - June 2025.18:37 13.07.2026 Petrovskie Vesti Network Edition - Petrovsk
The court confirmed the legality of the decision of the Khanty-Mansiysk OFAS to include LLC "Life+" in the RNP for unfair contract performance
LLC "Life+" repeatedly violated deadlines for the installation of the New Year's tree in the Central Square of the city.12:09 13.07.2026 OFAS - Khanty-Mansiysk
The prosecutor's office demands to recover 9.8 million rubles from the contractor for the failure to repair the road in Tambov
The Tambov Region Prosecutor's Office filed a lawsuit against LLC "SU 1". The Lipetsk contractor is being asked to recover 9.8 million rubles in damages for the failure of the municipal contract for the repair of the road on 2nd Vysotnaya Street in Tambov.00:02 13.07.2026 IA Tambov-Inform - Tambov
Другие Новости Нижнего (Н-Н-152)
The contract for the road in Arzamas for 2.6 billion rubles was not extended after the deadlines were missed.
11:59 July 14 Vasilieva Anna photo by "Pro Gorod" The Arbitration Court of the Nizhny Novgorod Region did not satisfy the claim of the St. Petersburg company LLC SK "Orion Plus," 07.14.2026. ProGorodNN.Ru. Nizhny Novgorod Region. Nizhny Novgorod.