The Auto Plant Thermal Power Station successfully passed the summer tests and confirmed its readiness for peak loads.

The Auto Plant Thermal Power Station successfully passed the summer tests and confirmed its readiness for peak loads.

      June 10, 2026 10:23 Society Avtozavodskaya CHPP (part of En+ Teplo Volga) successfully completed the summer certification procedure for electrical capacity. The official conclusion on the successful completion of the tests was issued by the System Operator of the Unified Energy System of Russia, which guarantees reliable energy supply to the region during peak consumption periods.

      The successful outcome was preceded by extensive preparatory work. The station's specialists developed a detailed training program for the certification, within which all planned preventive repairs were carried out and a comprehensive diagnosis of key technological units was conducted.

      During the tests, experts checked the readiness of all boiler units and turbines for operation in normal mode and under maximum loads. Both the main and auxiliary equipment underwent thorough checks for compliance with strict industrial safety requirements.

      The high certification results were aided by the station's modernization program. Recently, key elements of the heating equipment were replaced, an automated monitoring system for heating network parameters was implemented, and the gas regulation points were reconstructed.

      "The successful completion of the summer certification is an objective indicator of the readiness and reliability of our equipment to handle high loads, as well as a guarantee of the energy stability of the region," noted Acting General Director of Avtozavodskaya CHPP Vladimir Kulagin.

      The program for updating the CHPP infrastructure will continue, ensuring uninterrupted and quality energy supply to the region. The NIA "Nizhny Novgorod" has channels on Telegram and MAX. Subscribe to stay updated on major events, exclusive materials, and operational information. Copyright © 1999—2025 NIA "Nizhny Novgorod". When reprinting, a hyperlink to NIA "Nizhny Novgorod" is mandatory. This resource may contain materials 18+