Almost 100% of the new bridge components were brought to Pochaisky ravine.
August 5, 2025, 13:39
[187]
NIA "Nizhny Novgorod" Society — Sergey Bisheltov
In Potain Ravine of Nizhny Novgorod, where the landscaping of the terraced park is ongoing, 98% of the elements for the future pedestrian bridge have been delivered. This was reported to NIA "Nizhny Novgorod" by the municipal state institution "GUMMiD."
Construction work for the foundations of the bridge is currently ongoing at the site. The installation of structures will begin after these preparatory stages are completed.
The institution emphasized that the project timeline remains unchanged. According to the current municipal contract, completion of construction is planned for November 2025.
"Currently, no adjustments have been made to the deadlines for work," clarified GUMMiD.
It is worth recalling that the previous bridge over Potain Ravine was deemed аварийным (unsafe) and was dismantled, which happened in summer 2024.
It was also reported that the road on Oktyabrskaya Street was opened from August 2 on the section from Alekseevskaya Street to Lykova Damba. However, only for vehicles for now. Tram traffic will resume only after the work in the ravine is finished.
NIA "Nizhny Novgorod" has a Telegram channel. Subscribe to stay informed about major events, exclusive materials, and operational updates.
Copyright © 1999–2025 NIA "Nizhny Novgorod". When reproducing, a hyperlink to NIA "Nizhny Novgorod" is required. This resource may contain 18+ materials.
Другие Новости Нижнего (Н-Н-152)