More than 23 million rubles were recovered from the Nizhny Novgorod company for the FSB museum.
The Nizhny Novgorod company LLC "Standard" was ordered to pay back about 23 million rubles in unearned advances for the creation of a museum dedicated to the activities of the personnel training system of the state security agencies in Nizhny Novgorod. The relevant information was published in the case file of the Arbitration Court of the Nizhny Novgorod Region. The claims were filed by the ANO "Center 800," as the organization acted as the customer. According to the case file, in 2024, "Center 800" and LLC "Standard" signed two contracts. Under the first contract, "Standard" was supposed to prepare the premises on the third floor of the FGKOU Institute of the FSB of Russia located at Kazansky Highway, 2 in Nizhny Novgorod. "Center 800" paid an advance of 18.4 million rubles under the contract, but "Standard" did not complete the work for that amount. To determine the actual work performed, "Center 800" had to order an expert examination from the ANO "Center for Expertise of the Chamber of Commerce and Industry of the Nizhny Novgorod Region." According to the expert's conclusion, the estimated cost of the work performed by the defendant amounted to 10.35 million rubles. Thus, the amount of unearned advance exceeds 8 million rubles. In November 2025, the plaintiff sent a notice of contract termination to the contractor. It should be noted that the total amount of the contract was 23 million rubles. Under the second contract, "Standard" was supposed to supply exhibition furniture and equipment for 13.95 million rubles. The company was paid 9.76 million rubles, but it did not fulfill its obligations.
As a result, LLC "Standard" was ordered to pay 17.8 million rubles in debt, 3.76 million rubles in penalties, as well as interest and expenses for the examination and fees totaling 1.55 million rubles. Photo: IA "Nizhny Now"
Author:
Editorial nn-now
More news about the event:
"Center 800" recovered over 23 million rubles from the contractor of the FSB museum
21:28 July 1
Nina Serebryakova
Photo by AI progorodnn. 21:35 01.07.2026 ProGorodNN.Ru - Nizhny Novgorod
The Nizhny Novgorod company was ordered to return 23 million rubles for the FSB museum
The Arbitration Court of the Nizhny Novgorod Region satisfied the claim against LLC "Standard." The company was ordered to pay about 23 million rubles under the contracts, 20:56 01.07.2026 Otkryty Nizhny - Nizhny Novgorod
The Nizhny Novgorod company was ordered to return 23 million rubles for the FSB museum
The contractor failed to fulfill its obligations under two contracts, the Arbitration Court's decision has not yet entered into legal force. The Arbitration Court of the Nizhny Novgorod Region satisfied the claim against LLC "Standard." 18:02 01.07.2026 Newsroom24.Ru - Nizhny Novgorod
More than 23 million were recovered from the Nizhny Novgorod company for the FSB museum
Photo: Alexander Volozhanin
The Arbitration Court of the Nizhny Novgorod Region satisfied two claims from ANO "Center 800" against LLC "Standard" for the creation of a museum of the personnel training system of the state security agencies in Nizhny Novgorod. 15:55 01.07.2026 NIA Nizhny Novgorod - Nizhny Novgorod
23 million rubles were recovered by "Center 800" from the contractor for two contracts
The Arbitration Court satisfied the customer's claims due to unearned advances. 23 million rubles were recovered by "Center 800" from the contractor for two contracts. 15:27 01.07.2026 Komsomolskaya Pravda - Nizhny Novgorod
"Center 800" won 23,000,000 rubles from the contractor for the FSB museum
More than 23 million rubles were recovered from LLC "Standard" for unearned advances for the creation of a museum dedicated to the activities of the personnel training system of the state security agencies in Nizhny Novgorod. 15:17 01.07.2026 vGorodeN.Ru - Nizhny Novgorod
More than 23 million rubles were recovered from the Nizhny Novgorod company for the FSB museum
About 23 million rubles in unearned advances were recovered from the Nizhny Novgorod company LLC "Standard" for the creation of a museum dedicated to the activities of the personnel training system of the state security agencies in Nizhny Novgorod. 14:16 01.07.2026 IA Nizhny Now - Nizhny Novgorod
News from neighboring regions on the topic:
The Chelyabinsk builder initiated bankruptcy proceedings due to large debts
The Interdistrict Inspectorate of the Federal Tax Service of Russia No. 4 for the Republic of Bashkortostan filed a petition with the Arbitration Court of the Chelyabinsk Region to declare LLC "NBMStroy" bankrupt. 18:37 01.07.2026 Rakurs 32 - Bryansk
Kolyma construction pie: who divides the billions of the master plan and national projects?
Says Magadan, June 30, 2026. The Magadan region is experiencing an unprecedented construction boom. 14:52 30.06.2026 Network publication Says Magadan - Magadan
Другие Новости Нижнего (Н-Н-152)
More than 23 million rubles were recovered from the Nizhny Novgorod company for the FSB museum.
The Nizhny Novgorod company LLC "Standart" was ordered to pay about 23 million rubles in unearned advances for the creation of a museum dedicated to the activities of the personnel training system of the state security agencies in Nizhny Novgorod. 01.07.2026. IA Nizhny Now. Nizhny Novgorod region. Nizhny Novgorod.